What is the procedure for Development of Regional Impact determination / review?
DRI determination
- If Bulloch County determines that the development meets the threshold for a DRI, the County completes Form 1: Initial DRI Information form, which is sent to DCA and the Coastal Georgia Regional Development Center (RDC).
- Based in part on the information provided in the Initial DRI Information form, the RDC will determine whether or not the proposed development should be processed as a DRI. The County will notify the applicant if the RDC determines a DRI review is required.
DRI Review
- Applicant completes as much of Development of Regional Impact: Pre-Review Questionnaire as possible, pays County DRI fee ($5 per acre), and submits both to Bulloch County.
- Bulloch County submits Development of Regional Impact: Pre-Review Questionnaire and Form 2: DRI Review Initiation Request to the RDC.
- Within 5 days of receiving the completed DRI Review Initiation Request, the RDC will respond in writing to Bulloch County. If the form contains complete information, the RDC will respond with a Completeness Certification letter, which will signal the official beginning of the DRI Regional Review process. If the form does not contain all required information, Bulloch County will be so notified.
- At the same time the Completeness Certification is mailed, the RDC will mail a DRI Preliminary Report and Request for Comments to the appropriate government agencies and interested parties for review.
- The RDC then has 30 days to complete a Public Finding of whether or not the proposed DRI is considered to be in the best interest of the state. The RDC has 45 days if the finding will be not in the best interest of the state.
- All comments and findings are provided to Bulloch County and all other parties involved.
|